The restoration work on the S.S.753 road surface in Esino Lario was completed in just three days.
The works covered approximately 650 metres for a total of 20,000 m². On day 1, 5 cm of milling was carried out; over the next two days, 5 cm of modified 0/12 wearing course asphalt was laid to ensure better pavement bearing capacity performance.
The challenge for our teams was to ensure high-quality work despite all the logistical difficulties imposed by the conformation of the territory, consisting of hairpin bends and narrow sections, resulting in a reduced width of the carriageway for manoeuvring the operating machines.
The work was commissioned by Anas S.p.a.